Curtis & Champa Streets Walkway Improvements

ABOUT THE PROJECT

To update walkways and emergency drive lanes to meet updated ADA compliance requirements. Update landscaping and add seating to improve outdoor environment on campus. It will provide more accessible travel routes to all campus community members and create a more appealing outdoor experience on campus.  

Project Impacts & Updates

Champa Street between 10th St and 11th St (between Central Classroom Building and Cherry Creek) will be closed to all walkers, bikers and vehicles between May 28-July 30, 2025. Building access will not be impacted by this closure.

The Curtis Street phase of the project (Curtis St between 10th St and 11th St) is complete and will reopen for use May 27, 2025.

Project Overview

Anticipated construction startJanuary 2025
Anticipated construction endJuly 2025
Budget$1.7 Million
Funding sourceState of Colorado Controlled Maintenance funded project
Architect/
Engineer
Matrix
Contractor Growling Bear