Project B – PE & Events Building Update
Please see below updates and information on the PE & Events Building construction.
Project Description | Replacing Air Handling Units and the HVAC system in the PE/Events Building |
Construction Dates | December 2024 – December 2025 |
Budget | $8 Million |
Funding Source | State Capital Renewal Project |
Construction Impact Update
Phase 2: 3/31/25 – 8/15/2025
Spaces available for use, please reference map below:
Use entrance #1 to access:
- Gym lobby and Gym,
- Fitness gym & climbing wall,
- 1st floor locker rooms,
- Fitness loft,
- Athletic training room – room 213
Use entrance #2 to access
- Weight room,
- Room 113G,
- Multipurpose room – 111B