Posted
West Classroom Building Closures & Impacts
Starting January 15, 2026, and until the completion of construction on the MSU Denver Gina and Frank Day Health Institute Tower (estimated summer of 2027), there will be impacts to the West Classroom and the surrounding construction areas. Detailed impacts can be found below.
Noise Impacts
During the month of February, tree and sidewalk removal and foundation preparation will be underway, creating noise impacts to West Classroom. Noise levels during some of this work will be high and faculty and staff may want to consider remote work and classes. See the map, schedule and legend below.

Upcoming activity through March 20, 2026
During Regular Business Hours: Construction in progress, South of West Classroom Building
- Wednesday 2.25 – week of March 16: Drilled pier foundations 💥💥
Legend:

General Construction Impacts
- Construction fencing has been installed along Champa Street between 9th and 10th streets. There is no public access in this area during the duration of construction.
- A travel path for traffic on Champa from east to west is being established, and will be shared when available.
- A map of the construction area is here (click to enlarge):

- Through the duration of construction, the south and only stair in the West Classroom Building will be closed. Stair and elevators located in the Arts Building and Central Classroom Building can be used to access West Classroom 1st and 2nd Floors.
- Below are floor plans detailing access to the West Classroom, as well as an external look at elevator/stairwell access (click to enlarge):